Maxson Avenue Improvements Resident Meeting

The City has now bid the project and now construction is going to be starting on the Maxson Avenue Improvements Project (Elm-Miller). All American Concrete, Inc. was awarded the project. A meeting will be held at the Community Center on April 27, 2017 at 5:30 pm to go over the contact people during construction, construction phasing, schedule, driveway access, garbage and mail.

The project will include the new concrete paving, driveways aprons, sidewalk, storm sewer, sanitary sewer, and as well as water mains. It is anticipated the construction will begin on May 1, 2017 and will be completed in about one year.

If you have questions, please call the Veenstra & Kimm, Inc. Project Manager Jason McKenzie at 877-241-8010 or City Hall at 319-627-2418.

See attachments below for original letters in both English and Spanish.

PDF icon English VersionPDF: 266.92 KB
PDF icon Spanish VersionPDF: 275.11 KB
PDF: 266.92 KB